Olegivskiy residens logo
Share

Construction Progress — August 2026

progress of construction

In August 2026, the following works were carried out at the construction site:

Section 1:

  • Facade works — 68%
  • Facade works on the terraces of the 6th, 7th and 8th floors — 72%
  • Waterproofing of the first-floor terrace — 20%
  • Installation of apartment entrance doors from the 1st to the 8th floor — 90%
  • Tiling of balconies — 12%

Section 2:

  • Facade works — 55%
  • Plastering of walls in common areas from the 1st to the 8th floor — 98%
  • Tiling of balconies — 10%
  • Casting-in of utility pipelines (K1, V1, K2) in floor slabs — 5%

Section 3:

  • Installation of apartment entrance doors from the 1st to the 8th floor — 90%
  • Installation of electrical cable networks (DShK) — 95%
  • Plastering of walls in common areas from the 1st to the 8th floor — 98%
  • Casting-in of utility pipelines (K1, V1, K2) in floor slabs — 90%

Section 4:

  • Installation of apartment entrance doors from the 1st to the 8th floor — 90%
  • Waterproofing of the first-floor terrace — 20%
  • Facade works — 46%
  • Tiling of balconies — 10%
  • Installation of fire protection system cable networks — 100%

Section 5:

  • Facade works on the terraces of the 6th, 7th and 8th floors — 30%
  • Plastering of walls in common areas from the 1st to the 8th floor — 80%
  • Waterproofing of the first-floor terrace — 15%
  • Installation of apartment entrance doors from the 1st to the 8th floor — 80%
  • Tiling of balconies — 10%

Parking:

  • Installation of expansion joints on vertical structures — 85%
  • Installation of air ducts — 45%
  • Preparation of wall surfaces for painting — 10%
  • Installation of water supply systems — 65%
Stay tuned

Other news

  • Offers

    Special price for selected residence in OLEGIV Podil

  • Offers

    Modern History of Podil

  • progress of construction

    Construction Progress for July 2026

  • Offers

    24-Month Installment Plan and Discount Program