In August 2026, the following works were carried out at the construction site:
Section 1:
- Facade works — 68%
- Facade works on the terraces of the 6th, 7th and 8th floors — 72%
- Waterproofing of the first-floor terrace — 20%
- Installation of apartment entrance doors from the 1st to the 8th floor — 90%
- Tiling of balconies — 12%
Section 2:
- Facade works — 55%
- Plastering of walls in common areas from the 1st to the 8th floor — 98%
- Tiling of balconies — 10%
- Casting-in of utility pipelines (K1, V1, K2) in floor slabs — 5%
Section 3:
- Installation of apartment entrance doors from the 1st to the 8th floor — 90%
- Installation of electrical cable networks (DShK) — 95%
- Plastering of walls in common areas from the 1st to the 8th floor — 98%
- Casting-in of utility pipelines (K1, V1, K2) in floor slabs — 90%
Section 4:
- Installation of apartment entrance doors from the 1st to the 8th floor — 90%
- Waterproofing of the first-floor terrace — 20%
- Facade works — 46%
- Tiling of balconies — 10%
- Installation of fire protection system cable networks — 100%
Section 5:
- Facade works on the terraces of the 6th, 7th and 8th floors — 30%
- Plastering of walls in common areas from the 1st to the 8th floor — 80%
- Waterproofing of the first-floor terrace — 15%
- Installation of apartment entrance doors from the 1st to the 8th floor — 80%
- Tiling of balconies — 10%
Parking:
- Installation of expansion joints on vertical structures — 85%
- Installation of air ducts — 45%
- Preparation of wall surfaces for painting — 10%
- Installation of water supply systems — 65%