Construction progress for April 2024

progress of construction

The DIM company performs work at the construction site on the street. Olehivska, 36.

In April, the following works were performed at the construction site:

Section 1:

  • Reinforcement of concreting of vertical structures up to -0.000 - 90%

Section 2:

  • Reinforcement of concreting floors 1, 2 and structures - 100%
  • Reinforcement of concreting of the 3rd floor - 15%

Section 3:

  • Reinforcement of concreting floors 1, 2 and structures - 100%
  • Reinforcement of concreting of the 3rd floor - 15%

Section 4:

  • Reinforcement of concreting of vertical structures of the 1st floor - 100%

Section 5:

  • Reinforcement of concrete slab - 100%
Stay tuned

Other news

  • Offers

    Apartment of the Month with a Spacious Balcony. From $2100/m²

  • progress of construction

    Construction progress for September 2025

  • Offers

    All Inclusive offer. Special conditions for apartments and parking spaces

  • Offers

    Limited installments up to 5 years without overpayments