In April 2025, the following works were carried out at the construction site:
Section 1:
- Masonry of external and internal partition walls 1st floor - 90%, 3rd floor - 80%, 5th floor - 80%
Section 3:
- Masonry of external and internal walls 8th floor - 95%
- Installation of windows from 1st to 8th floor - 95%
- Installation of engineering systems, sewage and rainwater drainage has begun
Section 4:
- Masonry of external and internal walls 5th floor - 75%, 6th floor - 80%
Section 5:
- Masonry of external and internal walls 5th floor - 75%, 6th floor - 80%
- Installation of windows from 1st to 7th floor - 95%, 8th floor - 75%
Parking 1 zone:
- Arrangement of parking cover slab elevation -0.850 - 80%