Construction progress for April 2026

progress of construction

In April 2026, the following works were completed at the construction site:

Section 1:

  • Facade installation – 55%
  • Terrace works on the 6th, 7th, and 8th floors: waterproofing, insulation, and screed – 15%
  • Finishing of common areas according to the design project (3rd floor) – 5%
  • Installation of apartment entrance doors on the 3rd floor (show unit) – 75%
  • Insulation and reinforcement of ventilation shafts (roof level) – 55%
  • Brickwork of the stylobate part – 85%

Section 2:

  • Facade installation – 55%
  • Terrace works: waterproofing, insulation, and screed – 75%
  • Brickwork of the stylobate part – 85%
  • Insulation of ventilation shafts (roof level) – 85%

Section 3:

  • Facade installation – 45%
  • Insulation of ventilation shafts (roof level) – 85%
  • Brickwork of the stylobate part – 85%

Section 4:

  • Facade installation – 35%
  • Terrace works: waterproofing, insulation, and screed – 95%
  • Brickwork of the stylobate part – 65%
  • Insulation of ventilation shafts (roof level) – 85%

Section 5:

  • Facade installation – 35%
  • Terrace works on the 6th, 7th, and 8th floors: waterproofing, insulation, and screed – 95%

Parking:

  • Installation of K1/K2 systems (stormwater and sewage) – 60%
  • Brickwork of walls and partitions – 80%
  • Brickwork of the stylobate part (lobby exit) – 52%
  • Thermal insulation of parking ceilings – 50%
  • Brickwork of technical rooms (ITP, ventilation chamber, electrical room) – 90%
Stay tuned

Other news

  • News

    Price increase - summer 2026

  • progress of construction

    Construction progress for March 2026

  • progress of construction

    Construction progress for February 2026

  • Offers

    Apartment with a large terrace in installments up to 2 years