In April 2026, the following works were completed at the construction site:
Section 1:
- Facade installation – 55%
- Terrace works on the 6th, 7th, and 8th floors: waterproofing, insulation, and screed – 15%
- Finishing of common areas according to the design project (3rd floor) – 5%
- Installation of apartment entrance doors on the 3rd floor (show unit) – 75%
- Insulation and reinforcement of ventilation shafts (roof level) – 55%
- Brickwork of the stylobate part – 85%
Section 2:
- Facade installation – 55%
- Terrace works: waterproofing, insulation, and screed – 75%
- Brickwork of the stylobate part – 85%
- Insulation of ventilation shafts (roof level) – 85%
Section 3:
- Facade installation – 45%
- Insulation of ventilation shafts (roof level) – 85%
- Brickwork of the stylobate part – 85%
Section 4:
- Facade installation – 35%
- Terrace works: waterproofing, insulation, and screed – 95%
- Brickwork of the stylobate part – 65%
- Insulation of ventilation shafts (roof level) – 85%
Section 5:
- Facade installation – 35%
- Terrace works on the 6th, 7th, and 8th floors: waterproofing, insulation, and screed – 95%
Parking:
- Installation of K1/K2 systems (stormwater and sewage) – 60%
- Brickwork of walls and partitions – 80%
- Brickwork of the stylobate part (lobby exit) – 52%
- Thermal insulation of parking ceilings – 50%
- Brickwork of technical rooms (ITP, ventilation chamber, electrical room) – 90%