The DIM company performs work at the construction site on the street. Olehivska, 36.
In August 2024, the following works were performed at the construction site:
Section 1:
- Concreting reinforcement of vertical structures from 3 to 5 floors - 100%
- Reinforcement of concreting of the floor slab from 3 to 5 floors - 100%
Section 2:
- Concreting reinforcement of vertical structures 6, 7 floors - 100%
- Reinforcement of concreting of floor slabs 5, 6 floors - 100%
- Masonry of the external internal walls of partitions 1st floor - 95%
Section 3:
- Concreting reinforcement of vertical structures 6, 7 floors - 100%
- Reinforcement of concreting of floor slabs 6, 7 floors - 100%
- Masonry of the external/internal walls of partitions on the 1st floor - 95%
- Masonry of the external/internal walls of partitions on the 2nd floor - 25%
Section 4:
- Reinforcement of concreting of vertical structures 5th floor - 100%
- Masonry of the external internal walls of partitions 1st floor - 95%
Section 5:
- Concreting reinforcement of vertical structures 1st floor - 90%
- Reinforcement of concreting of the floor slab above the parking lot - 100%