Olegivskiy residens logo
Share

Construction progress for August 2024

progress of construction

The DIM company performs work at the construction site on the street. Olehivska, 36.

In August 2024, the following works were performed at the construction site:

Section 1:

  • Concreting reinforcement of vertical structures from 3 to 5 floors - 100%
  • Reinforcement of concreting of the floor slab from 3 to 5 floors - 100%

Section 2:

  • Concreting reinforcement of vertical structures 6, 7 floors - 100%
  • Reinforcement of concreting of floor slabs 5, 6 floors - 100%
  • Masonry of the external internal walls of partitions 1st floor - 95%

Section 3:

  • Concreting reinforcement of vertical structures 6, 7 floors - 100%
  • Reinforcement of concreting of floor slabs 6, 7 floors - 100%
  • Masonry of the external/internal walls of partitions on the 1st floor - 95%
  • Masonry of the external/internal walls of partitions on the 2nd floor - 25%

Section 4:

  • Reinforcement of concreting of vertical structures 5th floor - 100%
  • Masonry of the external internal walls of partitions 1st floor - 95%

Section 5:

  • Concreting reinforcement of vertical structures 1st floor - 90%
  • Reinforcement of concreting of the floor slab above the parking lot - 100%
Stay tuned

Other news

  • progress of construction

    Construction progress for June 2025

  • Offers

    Limited 10-Year Installment — Only for 10 Apartments

  • progress of construction

    Construction progress for May 2025

  • progress of construction

    Construction progress for April 2025