Construction progress for December 2023
OLEGIV Podil by DIM is under active construction.
In December, the following works were performed at the construction site:
Section 1:
- Reinforcement of concreting of vertical structures up to -0.000 - 75%
Section 3:
- Reinforcement of concreting of vertical structures up to -0.000 - 90%
Section 4:
- Reinforcement of concreting of vertical structures up to -0.000 - 90% (lower part)
- Reinforcement of concreting of the floor slab of the lower part of the building -4.950 – 28%
Parking I zone:
- Backfilling, soil compaction, preparation of the area of the section for the installation of the power plate - 80%
- Reinforcement of concreting pits in the underground part - 100%
- Reinforcement of concreting of the power plate - 75%
- Reinforcement of concreting of vertical structures up to - 20% (lower part)
Parking II zone:
- Concreting reinforcement of vertical structures up to -0.000 - 75% (lower part)
- Reinforcement of concreting of the floor slab of the lower part of the building -4.950 – 25%
Stay tuned
Other news
progress of construction
Construction progress for January 2025
1/31/2025
News
Monolithic Works Completed at OLEGIV Boutique Residence!
1/29/2025
Offers
Exclusive Apartments with Post-Completion Installment Plans
1/27/2025
Offers
Premium apartments in Podil with up to 3 years installment plan
1/27/2025