Construction progress for December 2025

progress of construction

In December 2025, the following works were carried out at the construction site:

Section 1:

  • Facade installation - 25%
  • Heating and water supply system installation on the 1st floor - 90%
  • Installation of ventilation equipment (valves) - 60%

Section 2:

  • Heating and water supply system installation on the 1st floor - 90%
  • Facade installation - 18%
  • Floor leveling in apartments and public areas on the 2nd and 3rd floors - 95%
  • Installation of ventilation equipment (valves) - 60%

Section 3:

  • Facade installation - 20%
  • Installation of ventilation equipment (valves) - 60%

Section 4:

  • Facade installation - 27%
  • Installation of ventilation equipment (valves) - 60%
  • Installation of elevator equipment - 80%
  • Heating and water supply system installation on the 1st floor - 90%
  • Floor leveling on the 1st floor - 90%

Section 5:

  • Facade installation - 25%
  • Heating and water supply system installation on the 1st floor - 90%
  • Floor leveling on the 1st floor - 90%
  • Installation of ventilation equipment (valves) - 60%

Parking:

  • Masonry of walls and partitions - 19%
Stay tuned

Other news

  • News

    5 spaces for business in OLEGIV Podil

  • News

    Price increase — from summer 2026

  • Offers

    7 selected apartments with a fireplace

  • Offers

    Panoramic terraces with views of Podil