Construction progress for February 2024

progress of construction

OLEGIV Podil by DIM is under active construction.

In February, the following works were performed at the construction site:

Section 1:

  • Reinforcement of concreting of vertical structures of the parking lot - 80%

Section 2:

  • Reinforcement of concreting of vertical structures of the parking lot - 90%

Section 3:

  • Reinforcement of concreting of vertical structures of the parking lot - 95%
  • Reinforcement of concreting of the parking floor slab - 95%

Section 4:

  • Reinforcement of concreting of the parking floor slab - 75% (lower part)

Parking II zone:

  • Reinforcement of concreting of vertical structures of the parking lot - 95% (lower part)
  • Reinforcement of concreting of the floor slab of the lower part of the parking lot - 95%
Stay tuned

Other news

  • Offers

    Premium apartments OLEGIV Podil in limited installments up to 10 years

  • progress of construction

    Construction progress for June 2025

  • Offers

    Limited 10-Year Installment — Only for 10 Apartments

  • progress of construction

    Construction progress for May 2025