In February 2025, the following construction work was completed on the site:
Section 1:
- Masonry of exterior and interior partition walls 5th floor – 85%, 6th floor – 90%, 7th floor – 90%, 8th floor – 95%
- Masonry of smoke extraction shafts – 80%
- Window installation from 1st-6th floor – 90%, 7th-8th floor – 75%
Section 2:
- Masonry of exterior and interior partition walls 5th floor – 75%, 6th floor – 70%, 7th floor – 20%, 8th floor – 10%
Section 3:
- Masonry of exterior and interior walls from 5th-6th floor – 90%, 7th floor – 85%, 8th floor – 75%
- Window installation 1st floor – 75%, 2nd floor – 75%, 3rd floor – 20%
Section 4:
- Masonry of exterior and interior walls from 4th-8th floor – 50%
- Masonry of smoke extraction shafts – 40%
Section 5:
- Masonry of exterior and interior walls from 4th-8th floor – 50%
- Masonry of smoke extraction shafts – 80%