Construction progress for Jenuary 2024

progress of construction

OLEGIV Podil by DIM is under active construction.

In January, the following works were performed at the construction site:

Section 1:

  • Reinforcement of concreting of vertical structures up to -0.000 - 80%

Section 2:

  • Reinforcement of concreting of vertical structures up to -0.000 - 80%

Section 3:

  • Concreting reinforcement of vertical structures up to -0.000 - 95%

Section 4:

  • Reinforcement of concreting of vertical structures up to -0.000 - 95% (lower part)

Parking I zone:

  • Backfilling, soil compaction, preparation of the area of the section for the installation of the power plate - 95%
  • Reinforcement of concrete slab - 90%

Parking II zone:

  • Reinforcement of concreting of vertical structures up to -0.000 - 90% (lower part)
  • Reinforcement of concreting of the floor slab of the lower part of the building -1,500 – 50%
Stay tuned

Other news

  • Offers

    Limited 10-Year Installment — Only for 10 Apartments

  • progress of construction

    Construction progress for May 2025

  • progress of construction

    Construction progress for April 2025

  • News

    DIM launches a special support program: new conditions for those approaching victory