In July, the following works were carried out on the construction site:
Section 3:
- Reinforcement of concreting of monolithic grid 4.1 – 95%
- Reinforcement of concreting of monolithic grid 3.1 – 95%
- Reinforcement of concreting of monolithic grid 4.2 – 95%
- Reinforcement of concreting of monolithic grid 4.3 – 95%
- Waterproofing of grills 4.1, 4.2, 4.3, 3.1 – 100%
Section 4:
- Reinforcement of concreting of monolithic grid 1 – 80%
- Reinforcement of piling - 90%
- Grill waterproofing 1 – 100%
Section 5:
- Reinforcement of piling, compaction planning and preparation for concreting - 75%
Parking:
- Reinforcement of concreting of monolithic grid 2.1 – 95%
- Reinforcement of concreting of monolithic grid 2.3 – 95%
- Reinforcement of concreting of the power plate of the parking lot of the 2nd part - 75%
- Waterproofing of grills 2.1, 2.3 – 100%