In July, the following works were carried out on the construction site:

Section 3:

  • Reinforcement of concreting of monolithic grid 4.1 – 95%
  • Reinforcement of concreting of monolithic grid 3.1 – 95%
  • Reinforcement of concreting of monolithic grid 4.2 – 95%
  • Reinforcement of concreting of monolithic grid 4.3 – 95%
  • Waterproofing of grills 4.1, 4.2, 4.3, 3.1 – 100%

Section 4:

  • Reinforcement of concreting of monolithic grid 1 – 80%
  • Reinforcement of piling - 90%
  • Grill waterproofing 1 – 100%

Section 5:

  • Reinforcement of piling, compaction planning and preparation for concreting - 75%

Parking:

  • Reinforcement of concreting of monolithic grid 2.1 – 95%
  • Reinforcement of concreting of monolithic grid 2.3 – 95%
  • Reinforcement of concreting of the power plate of the parking lot of the 2nd part - 75%
  • Waterproofing of grills 2.1, 2.3 – 100%
Stay tuned

Other news

  • Offers

    Limited 10-Year Installment — Only for 10 Apartments

  • progress of construction

    Construction progress for May 2025

  • progress of construction

    Construction progress for April 2025

  • News

    DIM launches a special support program: new conditions for those approaching victory