The DIM company performs work at the construction site on the street. Olehivska, 36.
In July 2024, the following works were performed at the construction site:
Section 1:
- Reinforcement of concreting of vertical structures of floor slabs 1, 2 floors - 100%
Section 2:
- Masonry of partition walls 1st floor - 25%
- Reinforcement of concreting of the 5th floor - 48%
Section 3:
- Reinforcement of concreting of vertical structures of floor slabs 4, 5, 6 floors - 100%
- Masonry of partition walls 1st floor - 55%
Section 4:
- Reinforcement of concreting of vertical structures of floor slabs 3, 4 floors - 100%
- Concreting reinforcement of vertical structures 5th floor - 40%
- Masonry of partition walls 1st floor - 55%
Section 5:
- Concreting reinforcement of vertical structures of the lower part of the section - 100%