Olegivskiy residens logo
Share

Construction Progress for July 2026

progress of construction

During July 2026, the following construction works were completed on site:

Section 1:

  • Façade installation — 65%
  • Finishing of common areas in accordance with the interior design (Level 3) — 90%
  • Plastering of common area walls (Levels 1–8) — 98%
  • Façade installation on terraces (Levels 6, 7 and 8) — 70%

Section 2:

  • Façade installation — 50%
  • Installation of paving (floor finish) on Level 7 terraces — 100%
  • Façade installation on Level 7 and 8 terraces — 20%
  • Plastering of common area walls (Levels 1–8) — 98%

Section 3:

  • Installation of fire protection system cabling — 100%
  • Installation of electrical cable networks (DSHK) — 95%
  • Plastering of common area walls (Levels 1–8) — 98%
  • Encasement of engineering pipelines (K1, V1, K2) within floor slabs — 90%

Section 4:

  • Façade installation — 45%
  • Installation of paving (floor finish) on Level 7 and 8 terraces — 100%
  • Finishing of roof ventilation shafts (thermal insulation and reinforcing layer) — 98%
  • Balcony floor tiling — 5%
  • Installation of electrical cable networks (DSHK) — 95%
  • Installation of fire protection system cabling — 100%
  • Plastering of common area walls (Levels 1–8) — 8%

Section 5:

  • Installation of paving (floor finish) on Level 6, 7 and 8 terraces — 100%
  • Finishing of roof ventilation shafts (thermal insulation and reinforcing layer) — 98%
  • Façade installation on Level 6, 7 and 8 terraces — 20%
  • Installation of fire protection system cabling — 100%
  • Plastering of common area walls (Levels 1–8) — 60%

Parking Garage:

  • Finishing of the ventilation plant room (wall and floor tiling) — 98%
  • Painting of parking garage ceilings — 80%
  • Installation of water supply systems — 60%
  • Installation of expansion joints on vertical structures — 60%
  • Ceiling surface preparation for painting — 90%
  • Installation of air ducts — 40%
  • Installation of the metal roof over the lobby — 98%
Stay tuned

Other news

  • News

    Modern History of Podil

  • Offers

    18-Month Installment Plan and Discount Program

  • Offers

    Live at the Peak of Podil

  • progress of construction

    Construction progress for June 2026