During July 2026, the following construction works were completed on site:
Section 1:
- Façade installation — 65%
- Finishing of common areas in accordance with the interior design (Level 3) — 90%
- Plastering of common area walls (Levels 1–8) — 98%
- Façade installation on terraces (Levels 6, 7 and 8) — 70%
Section 2:
- Façade installation — 50%
- Installation of paving (floor finish) on Level 7 terraces — 100%
- Façade installation on Level 7 and 8 terraces — 20%
- Plastering of common area walls (Levels 1–8) — 98%
Section 3:
- Installation of fire protection system cabling — 100%
- Installation of electrical cable networks (DSHK) — 95%
- Plastering of common area walls (Levels 1–8) — 98%
- Encasement of engineering pipelines (K1, V1, K2) within floor slabs — 90%
Section 4:
- Façade installation — 45%
- Installation of paving (floor finish) on Level 7 and 8 terraces — 100%
- Finishing of roof ventilation shafts (thermal insulation and reinforcing layer) — 98%
- Balcony floor tiling — 5%
- Installation of electrical cable networks (DSHK) — 95%
- Installation of fire protection system cabling — 100%
- Plastering of common area walls (Levels 1–8) — 8%
Section 5:
- Installation of paving (floor finish) on Level 6, 7 and 8 terraces — 100%
- Finishing of roof ventilation shafts (thermal insulation and reinforcing layer) — 98%
- Façade installation on Level 6, 7 and 8 terraces — 20%
- Installation of fire protection system cabling — 100%
- Plastering of common area walls (Levels 1–8) — 60%
Parking Garage:
- Finishing of the ventilation plant room (wall and floor tiling) — 98%
- Painting of parking garage ceilings — 80%
- Installation of water supply systems — 60%
- Installation of expansion joints on vertical structures — 60%
- Ceiling surface preparation for painting — 90%
- Installation of air ducts — 40%
- Installation of the metal roof over the lobby — 98%
Stay tuned