Construction Progress for July 2026

progress of construction

In July 2026, the following works were carried out at the construction site:

Section 1:

  • Façade works — 65%
  • Finishing of common areas according to the design project (3rd floor) — 90%
  • Plastering of common-area walls from the 1st to the 8th floor — 98%
  • Façade works on the terraces of the 6th, 7th and 8th floors — 70%

Section 2:

  • Façade works — 50%
  • Installation of paving elements (flooring) on the 7th-floor terraces — 100%
  • Façade works on the terraces of the 7th and 8th floors — 20%
  • Plastering of common-area walls from the 1st to the 8th floor — 98%

Section 3:

  • Installation of fire safety system cable networks — 100%
  • Installation of electrical cable networks (DSHK) — 95%
  • Plastering of common-area walls from the 1st to the 8th floor — 98%
  • Concreting-in of utility pipelines (K1, V1, K2) within floor slabs — 90%

Section 4:

  • Façade works — 45%
  • Installation of paving elements (flooring) on the terraces of the 7th and 8th floors — 100%
  • Finishing of rooftop ventilation shafts (insulation + reinforcement) — 98%
  • Balcony floor finishing (tiles) — 5%
  • Installation of electrical cable networks (DSHK) — 95%
  • Installation of fire safety system cable networks — 100%
  • Plastering of common-area walls from the 1st to the 8th floor — 98%

Section 5:

  • Installation of paving elements (flooring) on the terraces of the 6th, 7th and 8th floors — 100%
  • Finishing of rooftop ventilation shafts (insulation + reinforcement) — 98%
  • Façade works on the terraces of the 6th, 7th and 8th floors — 20%
  • Installation of fire safety system cable networks — 100%
  • Plastering of common-area walls from the 1st to the 8th floor — 60%

Parking

  • Finishing of the ventilation chamber (wall and floor tiling) — 98%
  • Painting of parking ceilings — 80%
  • Installation of water supply systems — 60%
  • Installation of expansion joints on vertical structures — 60%
  • Preparation of ceiling surfaces for painting — 90%
  • Installation of air ducts — 40%
  • Installation of the lobby roof (metal roofing) — 98%
Stay tuned

Other news

  • progress of construction

    Construction Progress — August 2026

  • Offers

    Special price for selected residence in OLEGIV Podil

  • Offers

    Modern History of Podil

  • Offers

    24-Month Installment Plan and Discount Program