Construction progress for June 2024

progress of construction

The DIM company performs work at the construction site on the street. Olegovskaya, 36.

In June 2024, the following work was carried out at the construction site:

Section 1:

  • Reinforcement of concreting vertical structures up to elevation -0.000 – 100%
  • Reinforcement for concreting the floor slab at elevation. -0100 and structures – 90%

Section 2:

  • Reinforcement of concreting 3, 4 floors and structures – 100%
  • Concreting reinforcement of the 5th floor – 45%

Section 3:

  • Concreting reinforcement of the 3rd floor – 100%
  • Concreting reinforcement of the 4th floor – 45%

Section 4:

  • Reinforcement of concreting of vertical structures of the 2nd floor – 100%
  • Reinforcement of concreting 3 floors and structures – 45%

Section 5:

  • Concreting reinforcement for vertical structures of the lower part of the section – 90%
Stay tuned

Other news

  • Offers

    Limited 10-Year Installment — Only for 10 Apartments

  • progress of construction

    Construction progress for May 2025

  • progress of construction

    Construction progress for April 2025

  • News

    DIM launches a special support program: new conditions for those approaching victory