Construction progress for June 2025

progress of construction

In June 2025, the following works were completed on the construction site:

Section 1:

  • Masonry of external and internal partition walls: 4th floor – 95%
  • Roofing – 95%
  • Installation of internal engineering networks for water supply, sewerage, and storm drainage – 75%
  • Installation of internal engineering systems (heating, water supply, electricity, low current) in apartments and common areas – 45%

Section 2:

  • Masonry of external and internal partition walls: 7th floor – 70%, 8th floor – 75%
  • Window installation: 1-4 floors – 95%, 6-8 floors – 85%, 9th floor – 95%
  • Masonry of smoke exhaust shafts on the roof – 50%

Section 3:

  • Masonry of smoke exhaust shafts on the roof – 100%
  • Installation of internal engineering networks for water supply, sewerage, and storm drainage – 80%
  • Installation of internal engineering networks for electricity and heat supply in apartments and common areas – 75%
  • Installation of sound insulation, floor in apartments, waterproofing in bathrooms and on balconies, and preparation of bases for cement screed – 75%

Section 4:

  • Masonry of external and internal walls: 1st floor – 85%, 3rd floor – 95%
  • Window installation: 2-8 floors – 95%

Section 5:

  • Masonry of external and internal walls: 1st floor – 75%, 3rd-4th floors – 95%
  • Roofing – 90%
  • Installation of internal engineering networks for water supply, sewerage, and storm drainage – 50%
Stay tuned

Other news

  • Offers

    Premium apartments OLEGIV Podil in limited installments up to 10 years

  • Offers

    Limited 10-Year Installment — Only for 10 Apartments

  • progress of construction

    Construction progress for May 2025

  • progress of construction

    Construction progress for April 2025