In June 2025, the following works were completed on the construction site:
Section 1:
- Masonry of external and internal partition walls: 4th floor – 95%
- Roofing – 95%
- Installation of internal engineering networks for water supply, sewerage, and storm drainage – 75%
- Installation of internal engineering systems (heating, water supply, electricity, low current) in apartments and common areas – 45%
Section 2:
- Masonry of external and internal partition walls: 7th floor – 70%, 8th floor – 75%
- Window installation: 1-4 floors – 95%, 6-8 floors – 85%, 9th floor – 95%
- Masonry of smoke exhaust shafts on the roof – 50%
Section 3:
- Masonry of smoke exhaust shafts on the roof – 100%
- Installation of internal engineering networks for water supply, sewerage, and storm drainage – 80%
- Installation of internal engineering networks for electricity and heat supply in apartments and common areas – 75%
- Installation of sound insulation, floor in apartments, waterproofing in bathrooms and on balconies, and preparation of bases for cement screed – 75%
Section 4:
- Masonry of external and internal walls: 1st floor – 85%, 3rd floor – 95%
- Window installation: 2-8 floors – 95%
Section 5:
- Masonry of external and internal walls: 1st floor – 75%, 3rd-4th floors – 95%
- Roofing – 90%
- Installation of internal engineering networks for water supply, sewerage, and storm drainage – 50%