In June 2026, the following works were completed at the construction site:
Section 1:
- Façade installation — 58%;
- Installation of paving slabs (terrace flooring) on the 6th, 7th, and 8th floors — 100%;
- Finishing of common areas in accordance with the interior design project (3rd floor) — 60%;
- Plastering of common area walls on floors 2–8 — 95%;
- Façade installation on the terraces of the 6th, 7th, and 8th floors — 65%.
Section 2:
- Façade installation — 48%;
- Installation of paving slabs (terrace flooring) on the 7th-floor terraces — 80%;
- Façade installation on the 7th- and 8th-floor terraces — 15%;
- Plastering of common area walls — 5%.
Section 4:
- Façade installation — 42%;
- Installation of paving slabs (terrace flooring) on the 7th- and 8th-floor terraces — 90%.
Section 5:
- Installation of paving slabs (terrace flooring) on the 6th, 7th, and 8th-floor terraces — 90%;
- Installation of thermal insulation and reinforcement of ventilation shafts (roof-mounted ventilation shafts) — 95%.
Parking Garage:
- Installation of K1/K2 systems (stormwater drainage and sewer systems) — 90%;
- Brick masonry of walls and partitions — 100%;
- Brick masonry of the podium structure (lobby exit) — 95%;
- Installation of thermal insulation for the parking garage ceilings — 100%;
- Installation of water supply systems — 50%;
- Installation of expansion joints on vertical structures — 50%;
- Plastering of walls (elevator lobby, ventilation room, security room, and parking garage walls) — 80%;
- Surface preparation of ceilings for painting — 20%.