Construction progress for June 2026

progress of construction

In June 2026, the following works were completed at the construction site:

Section 1:

  • Façade installation — 58%;
  • Installation of paving slabs (terrace flooring) on the 6th, 7th, and 8th floors — 100%;
  • Finishing of common areas in accordance with the interior design project (3rd floor) — 60%;
  • Plastering of common area walls on floors 2–8 — 95%;
  • Façade installation on the terraces of the 6th, 7th, and 8th floors — 65%.

Section 2:

  • Façade installation — 48%;
  • Installation of paving slabs (terrace flooring) on the 7th-floor terraces — 80%;
  • Façade installation on the 7th- and 8th-floor terraces — 15%;
  • Plastering of common area walls — 5%.

Section 4:

  • Façade installation — 42%;
  • Installation of paving slabs (terrace flooring) on the 7th- and 8th-floor terraces — 90%.

Section 5:

  • Installation of paving slabs (terrace flooring) on the 6th, 7th, and 8th-floor terraces — 90%;
  • Installation of thermal insulation and reinforcement of ventilation shafts (roof-mounted ventilation shafts) — 95%.

Parking Garage:

  • Installation of K1/K2 systems (stormwater drainage and sewer systems) — 90%;
  • Brick masonry of walls and partitions — 100%;
  • Brick masonry of the podium structure (lobby exit) — 95%;
  • Installation of thermal insulation for the parking garage ceilings — 100%;
  • Installation of water supply systems — 50%;
  • Installation of expansion joints on vertical structures — 50%;
  • Plastering of walls (elevator lobby, ventilation room, security room, and parking garage walls) — 80%;
  • Surface preparation of ceilings for painting — 20%.
Stay tuned

Other news

  • progress of construction

    Construction progress for May 2026

  • Offers

    Private residence with parking

  • News

    5 spaces for business in OLEGIV Podil

  • News

    Price increase — from summer 2026