Construction progress for March 2024

progress of construction

The DIM company performs work at the construction site on the street. Olehivska, 36.

In March, the following works were performed at the construction site:

Section 2:

  • Reinforcement of concreting of vertical structures, floor slabs 1st, 2nd floor - 95%

Section 3:

  • Reinforcement of concreting of vertical structures, floor slabs 1st, 2nd floor - 95%

Section 4:

  • Reinforcement of vertical structures of the first floor - 55%