Construction progress for March 2024

The DIM company performs work at the construction site on the street. Olehivska, 36.

In March, the following works were performed at the construction site:

Section 2:

  • Reinforcement of concreting of vertical structures, floor slabs 1st, 2nd floor - 95%

Section 3:

  • Reinforcement of concreting of vertical structures, floor slabs 1st, 2nd floor - 95%

Section 4:

  • Reinforcement of vertical structures of the first floor - 55%