In March 2025, the following works were carried out at the construction site:
Section 1:
- Masonry of external and internal walls of partitions 1st floor - 75%, 5th floor - 95%, 6th floor - 95%, 7th floor - 95%
- Masonry of smoke vent shafts - 95%
- Installation of windows on the 7th and 8th floors - 90%
Section 2:
- Masonry of external and internal walls of partitions 4th floor - 45%, 5th floor - 80%, 6th floor - 80%, 7th floor - 45%, 8th floor - 45%
Section 3:
- Masonry of external and internal walls 7th floor - 95%, 8th floor - 90%
- Installation of windows from 1st to 7th floor - 95%, 8th floor - 75%
Section 4:
- Masonry of external and internal walls 7th, 8th floor - 95%
- Masonry of smoke vent shafts - 100%
Section 5:
- Masonry of external and internal walls of 7th, 8th floor - 95%
- Masonry of smoke vent shafts - 100%
Parking 1st zone:
- Installation of slab beams of slab PP - 100%
Stay tuned