In March 2026, the following works were carried out at the construction site:
Section 1:
- Facade installation - 27%
- Waterproofing of ventilation shafts on the roof - 95%
- Installation of cement-sand screed on the 1st floor - 95%
- Brickwork of residential premises according to the design project on the 1st floor - 95%
- Insulation of ventilation shafts on the roof - 15%
Section 2:
- Waterproofing of ventilation shafts on the roof - 95%
- Installation of cement-sand screed on the 1st floor - 95%
- Brickwork of residential premises according to the design project on the 1st floor - 95%
- Insulation of ventilation shafts on the roof - 15%
Section 3:
- Facade installation - 25%
- Installation of engineering networks (V1, T3, OV, ETR) on the floor - 75%
- Installation of facade tiles - 75%
- Waterproofing of ventilation shafts on the roof - 95%
- Installation of cement-sand screed on the 1st floor - 95%
- Brickwork of residential premises according to the design project on the 1st floor - 95%
- Insulation of ventilation shafts on the roof - 55%
- Installation of ventilation equipment on the roof - 35%
Section 4:
- Waterproofing of ventilation shafts on the roof - 95%
- Brickwork of residential premises according to the design project on the 1st floor - 95%
- Insulation of ventilation shafts on the roof - 55%
Section 5:
- Terrace construction on floors 6-8 (waterproofing, insulation, screed) - 65%
- Waterproofing of ventilation shafts on the roof - 95%
- Brickwork of residential premises according to the design project on the 1st floor - 95%
- Insulation of ventilation shafts on the roof - 55%
Parking:
- Installation of K1/K2 (drainage, sewerage) - 15%
- Brickwork of walls and partitions - 5%
- Brickwork of the stylobate part - 50%