In May 2026, the following works were completed on the construction site:
Section 1:
- Facade installation — 58%
- Waterproofing of terraces on the 6th, 7th, and 8th floors (waterproofing, insulation, screed) — 100%
- Finishing of common areas according to the design project (3rd floor) — 30%
- Plastering of common area walls on the 2nd and 4th floors — 75%
- Insulation and reinforcement of ventilation shafts on the roof — 85%
- Waterproofing of ventilation shafts on the roof — 100%
- Brickwork of the stylobate part — 100%
- Installation of cable networks on walls before plastering of common areas — 90%
Section 2:
- Facade installation — 40%
- Waterproofing of terraces (waterproofing, insulation, screed) — 100%
- Insulation of ventilation shafts on the roof — 95%
- Brickwork of the stylobate part — 100%
Section 3:
- Facade installation — 48%
- Insulation of ventilation shafts on the roof — 95%
- Brickwork of the stylobate part — 100%
- Installation of decorative facade elements (rustication) — 35%
Section 4:
- Facade installation — 38%
- Waterproofing of terraces (waterproofing, insulation, screed) — 100%
- Insulation of ventilation shafts on the roof — 95%
- Brickwork of the stylobate part — 95%
- Finishing surface on terraces (FEM paving) — 20%
Section 5:
- Facade installation — 38%
- Terraces on the 6th, 7th, and 8th floors (waterproofing, insulation, screed) — 100%
- Insulation and reinforcement of ventilation shafts on the roof — 85%
Parking:
- Installation of K1/K2 (stormwater drainage, sewage) — 80%
- Brickwork of walls and partitions — 90%
- Brickwork of the stylobate part (lobby exit) — 80%
- Insulation of parking ceilings — 80%
- Brickwork of technical rooms (heating substation, ventilation chamber, electrical room) — 100%
- Cement-sand screed (elevator hall, ventilation chamber, security room) — 80%
- Wall plastering (elevator hall, ventilation chamber, security room, parking walls) — 20%