Construction progress for November 2023

progress of construction

OLEGIV Podil ot DIM is actively under construction.

In November, the following works were carried out at the construction site:

Section 3:

  • Reinforcement of concreting of vertical structures up to -0.000 – 75%

Section 4:

  • Concrete reinforcement of vertical structures (lower part) up to -0.000 – 60%
  • Reinforcement of concreting slabs of the lower part to the mark -4950 – 25%

Section 5:

  • Backfilling, compaction of the soil, preparation of the area of the section for the device of the power plate - 50%
  • Reinforcement of concreting pits in the underground part - 75%
  • Concrete reinforcement of the power plate - 75%
  • Construction of the channel of the underground part of the EO – 100%

Parking, I zone:

  • Soil compaction, preparation for the installation of a power plate - 20%
  • The device of the power plate - 20%

Parking, II zone:

  • Fence reinforcement device - 30%
  • Wall reinforcement - 25%
Stay tuned

Other news

  • News

    Live autonomously in the OLEGIV Podil club house

  • Offers

    Apartment of the Month with a Spacious Balcony. From $2100/m²

  • progress of construction

    Construction progress for September 2025

  • Offers

    Limited installments up to 5 years without overpayments