Construction progress for November 2023
OLEGIV Podil ot DIM is actively under construction.
In November, the following works were carried out at the construction site:
Section 3:
- Reinforcement of concreting of vertical structures up to -0.000 – 75%
Section 4:
- Concrete reinforcement of vertical structures (lower part) up to -0.000 – 60%
- Reinforcement of concreting slabs of the lower part to the mark -4950 – 25%
Section 5:
- Backfilling, compaction of the soil, preparation of the area of the section for the device of the power plate - 50%
- Reinforcement of concreting pits in the underground part - 75%
- Concrete reinforcement of the power plate - 75%
- Construction of the channel of the underground part of the EO – 100%
Parking, I zone:
- Soil compaction, preparation for the installation of a power plate - 20%
- The device of the power plate - 20%
Parking, II zone:
- Fence reinforcement device - 30%
- Wall reinforcement - 25%
Stay tuned
Other news
progress of construction
Construction progress for December 2024
12/30/2024
Offers
OLEGIV Podil – the art of living beautifully with favorable installments for 7 years
12/9/2024
progress of construction
Construction progress for November 2024
12/4/2024
Offers
Limited offer – residences in Podil for $1,500/month
12/3/2024