progress of construction
Construction progress for November 2023
OLEGIV Podil ot DIM is actively under construction.
In November, the following works were carried out at the construction site:
Section 3:
- Reinforcement of concreting of vertical structures up to -0.000 – 75%
Section 4:
- Concrete reinforcement of vertical structures (lower part) up to -0.000 – 60%
- Reinforcement of concreting slabs of the lower part to the mark -4950 – 25%
Section 5:
- Backfilling, compaction of the soil, preparation of the area of the section for the device of the power plate - 50%
- Reinforcement of concreting pits in the underground part - 75%
- Concrete reinforcement of the power plate - 75%
- Construction of the channel of the underground part of the EO – 100%
Parking, I zone:
- Soil compaction, preparation for the installation of a power plate - 20%
- The device of the power plate - 20%
Parking, II zone:
- Fence reinforcement device - 30%
- Wall reinforcement - 25%
Stay tuned
Other news
progress of construction
Construction progress for April 2024
03.05.2024
Offers
Live better in Podil in the OLEGIV Podil clubhouse
07.04.2024
Offers
Do you work in Podol? Live in OLEGIV Podil!
05.04.2024
progress of construction
Construction progress for March 2024
04.04.2024