Construction progress for November 2024

In November 2024, the following works were performed at the construction site:

Section 1:

  • Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell – 100%
  • Reinforcement of concreting of the floor slab of the 8th floor from +25.895 – 100%
  • Masonry of the external internal walls of partitions from the 1st to the 5th floor – 50%

Section 2:

  • Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell - 100%
  • Masonry of the external internal walls of the partitions on the 3rd floor – 100%

Section 3:

  • Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell - 100%
  • Masonry of external internal walls 3rd floor – 100%, 4th floor – 90%, 5th floor – 5%

Section 4:

  • Reinforcement of concreting of vertical structures, floor slabs, 8th floor – 100%

Section 5:

  • Concreting reinforcement of vertical structures 5th, 6th, 7th floor -– 100%

Stay tuned

Other news

  • Offers

    OLEGIV Podil – the art of living beautifully with favorable installments for 7 years

    12/9/2024

  • Offers

    Exclusive program – apartments on your own terms

    12/4/2024

  • Offers

    Limited offer – residences in Podil for $1,500/month

    12/3/2024

  • Offers

    Financial guarantees for OLEGIV Boutique Residence

    11/25/2024