progress of construction
Construction progress for November 2024
In November 2024, the following works were performed at the construction site:
Section 1:
- Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell – 100%
- Reinforcement of concreting of the floor slab of the 8th floor from +25.895 – 100%
- Masonry of the external internal walls of partitions from the 1st to the 5th floor – 50%
Section 2:
- Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell - 100%
- Masonry of the external internal walls of the partitions on the 3rd floor – 100%
Section 3:
- Concrete reinforcement of the structure on the roof of the elevator shaft and stairwell - 100%
- Masonry of external internal walls 3rd floor – 100%, 4th floor – 90%, 5th floor – 5%
Section 4:
- Reinforcement of concreting of vertical structures, floor slabs, 8th floor – 100%
Section 5:
- Concreting reinforcement of vertical structures 5th, 6th, 7th floor -– 100%
Stay tuned
Other news
Offers
OLEGIV Podil – the art of living beautifully with favorable installments for 7 years
12/9/2024
Offers
Exclusive program – apartments on your own terms
12/4/2024
Offers
Limited offer – residences in Podil for $1,500/month
12/3/2024
Offers
Financial guarantees for OLEGIV Boutique Residence
11/25/2024