In November 2025, the following work was completed at the construction site:
Section 1:
- Facade installation – 20%
- Roof installation – 25% at +29,450
- Installation of ventilation equipment (valve) – 25%
Section 2:
- Roof installation – 80% at +29,450 and at +28,000
- Installation of engineering networks in the screed – 20%
- Facade installation – 15%
- Installation of K1 risers – 100%
- Installation of screed in apartments and MZK from 4 to 8 floors – 90%
Section 3:
- Installation of elevator equipment – 85%
- Installation of the roof in the area of R-P/8-11 at +26,600 – 100% and at +29,450 and from +28,000 – 80%
- Facade construction – 19%
- Installation of outdoor lighting on the facade – 20%
Section 4:
- Facade construction – 25%
- Roof construction – 80% on from +29,450 and on from +28,000
- Installation of K1 risers – 100%
- Installation of outdoor lighting on the facade – 25%
- Installation of basket brackets for air conditioners – 80%
Section 5:
- Facade construction – 22%
- Roof construction – 20% from +29,450
- Installation of K1 risers – 50%
- Installation of outdoor lighting on the facade – 20%
Parking:
- Masonry of walls and partitions – 17%