Construction progress for October 2023
Club house OLEGIV Podil from the company DIM is under construction.
In October, the following works were performed at the construction site:
Section 4:
- Reinforcement of concrete slab - 90%
- Reinforcement of concreting of the vertical structures of the walls of the underground part - 35%
Section 5:
- Concreting reinforcement of the EO channel in the underground part – 85%
- Concreting reinforcement of strip grid - 100%
- Reinforcement of concreting of the vertical structures of the walls of the underground part - 45%
Parking:
- Concreting reinforcement of the channel in the underground part - 100%
- Preparation of the area of the section for the installation of foundations - 52%
- Concreting the foundations of the grills - 50%
Stay tuned
Other news
Offers
Independence from the course is a new program from DIM
08.11.2023
Offers
Black Friday every day
03.11.2023
Offers
Individual installments for apartments
02.11.2023
Offers
Apartments with a profit from UAH 600,000
20.10.2023