Construction progress for October 2024

DIM company is performing work at the construction site on the street. Olegivska, 36.

In October 2024, the following works were performed at the construction site:

Section 1:

  • Reinforcement of concreting of vertical structures from 7 to 8 floors and parapets - 100%
  • Reinforcement of concreting of floor slabs from 6 to 7 floors - 100%

Section 2:

  • Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
  • Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 60%

Section 3:

  • Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
  • Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 80%

Section 4:

  • Reinforcement of concreting of vertical structures, floor slabs 6, 7 floors – 100%
  • Masonry of external and internal walls of partitions 1 floor – 100%

Section 5:

  • Reinforcement of concreting of vertical structures 3, 4 floors – 100%

Stay tuned

Other news

  • progress of construction

    Construction progress for November 2024

    12/4/2024

  • Offers

    Exclusive program – apartments on your own terms

    12/4/2024

  • Offers

    Limited offer – residences in Podil for $1,500/month

    12/3/2024

  • Offers

    Financial guarantees for OLEGIV Boutique Residence

    11/25/2024