DIM company is performing work at the construction site on the street. Olegivska, 36.
In October 2024, the following works were performed at the construction site:
Section 1:
- Reinforcement of concreting of vertical structures from 7 to 8 floors and parapets - 100%
- Reinforcement of concreting of floor slabs from 6 to 7 floors - 100%
Section 2:
- Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
- Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 60%
Section 3:
- Reinforcement of concreting of vertical structures of floor slabs 7, 8 floors, parapets and roof structures - 100%
- Masonry of external and internal walls of partitions 1, 2 floors - 100% and 3 floors - 80%
Section 4:
- Reinforcement of concreting of vertical structures, floor slabs 6, 7 floors – 100%
- Masonry of external and internal walls of partitions 1 floor – 100%
Section 5:
- Reinforcement of concreting of vertical structures 3, 4 floors – 100%