Construction progress for September 2023

progress of construction

Club house OLEGIV Podil from the company DIM is under construction.

In September, the following works were performed at the construction site:

Section 4:

  • Reinforcement of concreting of the grid - 80%

Section 5:

  • Reinforcement of the grillwork concreting - 75%
  • Waterproofing of the grill - 75%

Parking:

  • Reinforcement of the grillwork concreting - 25%
  • Reinforcement of concreting of vertical structures of the underground part - 10%
  • Waterproofing of the grill - 75%
Stay tuned