Construction progress for September 2024

The DIM company performs work at the construction site on the street. Olehivska, 36.

In September 2024, the following works were performed at the construction site:

Section 1:

  • Concreting reinforcement of vertical structures from the 6th to the 7th floor and the parapet - 100%
  • Reinforcement of concreting of the floor slab from the 6th to the 7th floors. - 100%

Section 2:

  • Reinforcement of concreting of vertical structures of the 7th floor and parapet - 100%
  • Reinforcement of concreting of the floor slab of the 7th floor - 100%
  • Masonry of the external internal walls of the partitions of the 2nd floor - 75%

Section 3:

  • Reinforcement of concreting of vertical structures of the 8th floor and parapet - 100%
  • Reinforcement of concreting of the floor slab of the 8th floor - 100%
  • Masonry of the external internal walls of the partitions of the 2nd floor - 85%

Section 4:

  • Reinforcement of concreting of vertical structures of the 6th floor - 100%
  • Reinforcement of concreting of the floor slab of the 5th floor - 100%

Section 5:

  • Concreting reinforcement of vertical structures of the 1st and 2nd floors - 100%
  • Reinforcement of concreting of the floor slab of the 1st floor - 100%

Stay tuned

Other news

  • Offers

    Exclusive apartments with fireplaces

    10/14/2024

  • Offers

    The last penthouse on the 7th floor

    10/11/2024

  • Offers

    Exclusive installments after the house is ready

    9/12/2024

  • Offers

    The last apartments with terraces on the top of Podol

    9/12/2024