The DIM company performs work at the construction site on the street. Olehivska, 36.
In September 2024, the following works were performed at the construction site:
Section 1:
- Concreting reinforcement of vertical structures from the 6th to the 7th floor and the parapet - 100%
- Reinforcement of concreting of the floor slab from the 6th to the 7th floors - 100%
Section 2:
- Reinforcement of concreting of vertical structures of the 7th floor and parapet - 100%
- Reinforcement of concreting of the floor slab of the 7th floor - 100%
- Masonry of the external internal walls of the partitions of the 2nd floor - 75%
Section 3:
- Reinforcement of concreting of vertical structures of the 8th floor and parapet - 100%
- Reinforcement of concreting of the floor slab of the 8th floor - 100%
- Masonry of the external internal walls of the partitions of the 2nd floor - 85%
Section 4:
- Reinforcement of concreting of vertical structures of the 6th floor - 100%
- Reinforcement of concreting of the floor slab of the 5th floor - 100%
Section 5:
- Concreting reinforcement of vertical structures of the 1st and 2nd floors - 100%
- Reinforcement of concreting of the floor slab of the 1st floor - 100%